Works on site have gone up a gear over the past two weeks with the structural steel progressing sufficiently to enable some of the other trades to commence their works. This has included installation of the plywood flooring to the upper level of the administration area along with the wall partitions on the ground level starting to go in as well. Over the next week or so the timber roof trusses will be installed over the administration area which will enable the roof sheeting to go on soon after that. All in all construction is progressing well and we expect to see some significant progress over coming weeks.
Col Wood, Project Manager