Palm Island Channel Dredging

Send to a Friend Bookmark this Page Sitemap

Client: Department of Main Roads, Queensland

Scope of Work:

  • Dredging of approximately 11,000m3 from the entrance channel and swing basin that provides access to the Palm Island jetty and barge ramp.
  • Transport and deposit dredge spoil by transport barge and truck to Townsville Port Authority land fill site.
  • Removal of existing and installation of new navigation beacons.

Time: January 09 to May 09

Contract Value: $2.5 Million

Project Photos

Loading slider…