  • Install 5km of 550mm diameter HDPE pipeline between Townsville and Magnetic Island, in a trench, and fully backfilled.

  • In House development of pipelay system. This involved a 30m flat top barge that was converted to jet the trench, install the weight blocks, launch the pipeline down the stinger into the trench, and backfill the trench.

  • Install 2 landward tie in sections

  • All pipe welding (into 300m strings), pressure testing, connections on the deck of the barge, and pigging and sterilisation.

Make an Enquiry

BACK TO PROJECTS

Client
NQ Water

Time
2005

Contract Value
5M