Berth 6/7 Demolition Update

The job continues to go well, with all of the conveyors / galleries / shiploader and concrete structure now removed, and the last of the piles being extracted. The major dredging campaign is about to begin. Sheerlegs has had some new forward scanning sonar technnology installed ready for many months of solid dredging.

The on site team has been doing a fantastic job throughout the whole job, achieving great safety and productivity results. A few photos from late July 2015.