Hay Point Stacker Reclaimers Delivery Continues

Work continues on the Hay Point Stacker Reclaimer Delivery job for our PMG Tarka, PMG 182, Swordfish and a dedicated crew of professionals who are working day and night to get this job finished in what has been an exceptional weather window. The overall job involves delivery of 2 x new stacker reclaimers, spread out over 18 bargeloads running between Mackay and Hay Point. After the 1st Stacker Reclaimer was successfully delivered, the heavy lift vessel sailed back to China to pick up the 2nd. So far 6 of the 9 bargeloads have been delivered for the 2nd Stacker Reclaimer, so work is expected to be complete within a week. A few pics of the 2nd Stacker Reclaimer deliveries to date are shown here.