Port Moresby Ocean Outfall Update

Progress continues at a rapid pace for the POMSSUP Ocean Outfall Pipeline with site personnel fine tuning installation systems. Works are commencing on schedule for the land to ocean transition area and pipeline installation will soon be just 70m from the land connection after starting over 900m from the this point just 6 weeks ago. The team is on track to have the ocean outfall connected to the main pipeline by the end of May for our client to commence commissioning trials.

The team will transition to ocean trench backfill operations during the transition area works which should see the project all but wrapped up in June well ahead of our August deadline.