Amrun Project River Terminals

Scope of work

  • Transport to Weipa 50 000T of rock / pavements / pipes / equipment. This was achieved with 4 x tug and barge sets, running from PMG’s Townsville Marine Facility
  • Provision of temporary berthing facilities (spudded barge dock) on site to allow barge unloading to be achieved on a greenfield river bank
  • Provision of cyclone moorings
  • Driving of 50 steel tubular piles to support the river facilities construction. 750mm diameter to 1050mm diameter, 25 – 40m long, vertical and raking piles
  • Complex piling requirements including extremely accurate tolerances, detailed QA requirements, electronic iPiler reporting and energy monitoring throughout each drive, full PDA testing requirements.

Make an Enquiry

BACK TO PROJECTS

Client
Goodline

Time
Jan - Aug 2016

Contract Value
7M